Project Area 36 DHQ MCs in the Punjab
Duration: 03 Year (FY 2019-20 - 2022-23)
Project Cost: PKR 371.193 Million
Objectives
- Improved service delivery through Smart Performance Management
- Integration of all systems into one consolidated dashboard
Salient Features
- Automating entire/partial service delivery office by linking online applications to department interfaces and tracking of applications wherever applicable.
- Feedback/Complaint mechanism embedded into system defined processes
- Monitoring of service delivery process through system available data: turn-around time, tracking, payments, feedback
- Computer generated documents and connected central databases at government level
Progress to date
- Team deployed
- Implementation Plan approved
- Client Server based architecture completed
- Work on following systems - in progress
- Financial Management System
- Moveable Assets Management System
- Municipal Assets Management Information System (Immovable)
- To date progress – rated as Satisfactory